Giovanni Gracias, Ground Partner from San Diego, California

12081 Calle De Medio

  • We are nearing the completion of this project but will have to delay our open house until 7/25. We are still missiing 3 custom kitchen cabinets to arrive from the manufacturer. 
  • All finish material has been purchased and stager has been scheduled for friday 7/24

 

4748 College Ave

  • We have completed the first 2 weeks of rehab and things are moving quickly.
  • The foundation has been repaired, plans for the room addition have been approved and we are moving towards framing and opening wall according to our plans. 
  • Electrical and plumbing upgrades taking place this week along with all exterior paint
  • Projected project timeline is 5 weeks. 

 

2672 Escala Circle

  • Closed on this property monday 7/6 and the scope of work requires approximitely $10K in rehab costs
  • Projected project timeline is 2-3 weeks however since the property was a short sale the bank required that I cannot sell it for 90 days from the day I purchased it.
  • We will do all work and begin marketing this property prior to the 90 days. We will be on the MLS  in 30-45 days. 